| Investor | Ban QLDA Khu đô thị mới Tây Ninh |
|---|---|
| Location | Tay Ninh City |
| Scale | 2×1000 kVA substation with underground MV cabling |
| Scope of work | Electrical infrastructure · Water supply & drainage |
| Region | Tay Ninh |
| Timeline | 01/2024 – 11/2024 |
Technical infrastructure for a new residential zone: a 2×1000 kVA substation, underground MV cabling feeding the whole area, and internal water supply and drainage networks.
Works ran in parallel with road infrastructure, requiring close coordination with the PM board and the local power utility to energize on schedule.